Construction

Ground was broken on January 20 as construction began on the pavilion space adjacent to the gallery.

Construction progress will be arranged by date.

Comments or questions? e-mail us

Week of January 20 DEMOLITION

Week of January 26 DEMOLITION

Week of February 9 CONCRETE POUR

Week of February 16 FRENCH DRAIN/FOOTINGS

Week of February 23 SONITUBE POURING + DECK FRAMING

Week of March 1  PAVILION WALL STRUCTURE + TAR

Week of March 8 PAVILION WALL DECKING + KNUCKLE ROOF

March & April Coming Soon

Week of April 12 CHIMNEY DEMOLITION

June & July Coming Soon

Week of June 21 VEGETABLE CLEANING PAVILION

COMING SOON Week of July  VEGETABLE CLEANING PAVILION

Week of August 2  PACKAGING SLAB FRAMING

NEW Week of September 6  PACKAGING ROOF + SHEATHING

 

 

 

 